Before a two-wheeler battery swap station opens to riders, it needs more than a power-on test. The site, cabinet, batteries, rider flow, and operations platform must work together—and the local team must know what happens when a swap fails, the connection drops, or an alarm is raised. This checklist covers the checks, records, and sign-offs needed before go-live. At HelloSwap, we build integrated swap systems for reliable day-to-day operation.

Start by assigning a commissioning lead. This person coordinates the site host, installer, electrical contractor, operations team, and equipment supplier, while maintaining one record of test results and open issues.
Before power is applied, confirm that the installed station matches the approved layout and can be accessed safely by riders, technicians, and emergency responders.
Check area | What to verify |
Cabinet location | The cabinet is installed in the approved position, clear of vehicle impact risks, drainage paths, public obstructions, and emergency routes |
Installation condition | Anchoring, enclosure, cable routing, weather protection, labels, and surrounding finishes are complete and undamaged |
Rider access | Riders can approach, queue, swap, and leave without obstructing traffic, pedestrians, shop entrances, or site operations |
Service access | Authorized technicians can safely access service panels and carry out inspections or repairs |
Site contacts | The site manager, landlord or host, electrical contact, local operations lead, and emergency contacts are confirmed |
Handover records | Site photos, as-built layout, equipment serial numbers, installation records, and open-item list are stored centrally |
Record installation defects for closeout. Safety-critical issues, including incomplete electrical work, damaged equipment, inadequate access, or missing emergency arrangements, must be resolved before commercial launch.
Electrical and communications checks should be completed by qualified personnel in line with the approved design, local requirements, and equipment documentation.
Before energizing the station, confirm that:
The incoming supply matches the approved cabinet configuration.
Dedicated circuits, protective devices, cables, isolators, and labels are correctly installed.
Earthing and bonding tests have been completed and recorded.
There is no visible cable damage, loose termination, water ingress, or exposed conductive part.
The emergency isolation point is identified and understood by the responsible site team.
Mobile network and/or Wi-Fi signal is stable where the cabinet is installed.
Confirm that the cabinet establishes and maintains a connection to the operations platform under the correct station identity. Record any connection loss, unstable signal, or configuration issue before functional testing begins.
Once the cabinet is energized and connected to the platform, confirm that its controllers and relevant modules are running the approved production firmware version. Then test each bay with approved batteries and authorized test accounts. Use the table below to record the result against each pass criterion.
Test | Pass criterion |
Battery insertion | The cabinet identifies an approved battery and assigns it to the correct bay |
Charging start | Charging begins only when the battery and bay meet configured operating conditions |
Battery data | Battery identity, state of charge, temperature, and charging status appear correctly in the platform |
Battery release | An eligible battery is released only after valid rider or operator authorization |
Door operation | Each door opens, closes, locks, and reports its status correctly |
Inventory status | The platform distinguishes available, charging, unavailable, and exception batteries correctly |
Remote visibility | Authorized personnel can view cabinet, bay, and battery status remotely |
Alarm reporting | Configured power, network, door, temperature, smoke, tamper, and battery-related alerts reach the designated team |
Where the operating model allows, repeat the relevant tests with batteries at representative states of charge.
The rider test should reflect the planned launch model, including the intended vehicle, battery, rider account, app or access method, and payment rules. A technician completing a manual test is not a substitute for a rider completing the normal journey independently.
Run and record the following sequence:
Rider registration or account authentication.
Station selection or discovery in the rider app, where applicable.
QR-code scan, NFC, Bluetooth, or other approved swap initiation.
Return of an eligible depleted battery.
Release and collection of an eligible charged battery.
Vehicle power-on and basic compatibility check.
Transaction completion, rider notification, and account update.
Accurate updates to battery inventory, payment records, and the operations dashboard.
If the business model uses subscriptions, deposits, credit limits, late-return rules, or pay-per-swap billing, test these conditions before opening the station. Back-office configuration alone does not prove that commercial rules work correctly in the live environment.

Commissioning should also cover situations that interrupt a normal swap or require the station to protect a battery, bay, or rider.
Test the following scenarios:
An unauthorized or incompatible battery is inserted.
A rider begins a transaction but does not complete the return process.
A bay door fails to close, lock, or report its status.
A battery is present but cannot charge or cannot be released.
Network connectivity is lost before or during a transaction.
Site power is interrupted and restored.
The station has insufficient eligible charged batteries.
An alarm is received from a fitted temperature, smoke, tamper, or other safety-monitoring device.
A rider requests support during an incomplete transaction.
Note: Use only manufacturer-approved methods or safe simulations when testing the system's response to an unauthorized, incompatible, or abnormal battery, or to a safety-related alarm. Any action to stop charging, isolate a bay, or disconnect power must follow the approved site design and equipment configuration.
For each scenario, record the following:
Check | What to confirm |
Cabinet response | The cabinet stops, locks, isolates, or recovers as configured |
Rider message | The rider receives a clear next step or support instruction |
Platform record | The event appears with accurate status, timestamp, and asset information |
Escalation path | The designated operations or maintenance contact receives the alert and knows what action to take |
Recovery | The transaction, station, or affected bay returns to service only after the required checks are complete |
Keep an emergency reference at the site with contact numbers, the station address, cabinet identification, isolation procedure, and the rule for when a cabinet or bay must remain unavailable until inspection is complete.
Go-live should be a documented decision, not an informal conclusion that the station appears ready. Before the first commercial swap, review the commissioning record with the relevant project, operations, and site stakeholders.
The final package should include:
Station location, cabinet model, and equipment serial numbers
Installation, electrical, connectivity, and platform-test records
Bay-by-bay functional test results
Rider journey and commercial-rule test results
Exception-test results, open issues, assigned owners, and closure plans
Initial battery inventory and replenishment responsibility
Emergency contacts and operating escalation process
Go-live approval from relevant stakeholders
Treat the first seven days as a stabilization period. Review swap success rate, battery availability, charging progress, door faults, network stability, alarm history, rider-support requests, and abnormal battery events daily.
Use this review to identify repeatable issues early, before they are carried into the next station deployment.